Project Status and Construction Budget for Projects > $50M

 

Project PIN

Project
Description

Initial Planned
Completion Date

Current
Completion Date

Initial Construction Budget

Approved Changes

Current Construction Budget

808601

Upgrade of Rt. 17: Exit 116 - 122

12/31/2010

9/30/2011

$62,986,000

$5,324,000

$68,311,000

906674

Rt. 17 at Parksville

10/1/2012

10/1/2012

$94,771,000

$1,856,000

$96,626,000

606658

Rt. 17 Elmira to Chemung

11/30/2012

11/30/2012

$64,656,000

$636,000

$65,292,000

950061

Rt. 17/I86 – Prospect Mountain

12/31/2015

12/31/2015

$134,686,000

$0

$134,686,000

800672

Rt. 17 – Exit 122, Stage 2

12/31/2013

12/31/2013

$72,350,000

$0

$72,350,000

 

 

Other Associated Projects

 

Project PIN

Project Description

Status

800673

Rt. 17 – Exit 122, Stage 3

In Development

800696

Rt. 17 – Exit 131, Stage 1

In Development

800684

Rt. 17 – Exit 131, Stage 2

In Development

906687

RTE 17/I86 Exit 106 Interchange Reconst

Under Construction

906725

RTE 17/I86 Interchange - Prospect High Mast Lighting, Phase 0

Project Complete

906674

RTE 17 @ Parksville

Under Construction

906695

RTE. 17/I86 Interchange Imp. Exits, 94, 96, 97 & 99

Project Complete

906742

RTE 17/I86 Interchange - Phase 0A

Project Complete

906735

RTE 17 @ Parksville, Phase 2

In Development

950061

RTE 17/I86 Inter Reconst Phase I (Prospect MTN)

Under Construction

950106

RTE 17/I86 Interchange Reconst Phase 2A (micropile)

Under Construction

950080

RTE 17/I86 Interchange Reconst Phase II

In Development

980441

I86 Signing Binghamton Area

In Development

906691

RTE 17/I86 Conversion Hale Eddy to Hancock

In Development

906729

RTE 17/I86 Conversion Tioga County

In Development