Project Status and Construction Budget for Projects > $50M
Project PIN |
Project |
Initial Planned |
Current |
Initial Construction Budget |
Approved Changes |
Current Construction Budget |
808601 |
12/31/2010 |
9/30/2011 |
$62,986,000 |
$5,324,000 |
$68,311,000 |
|
906674 |
10/1/2012 |
10/1/2012 |
$94,771,000 |
$1,856,000 |
$96,626,000 |
|
606658 |
11/30/2012 |
11/30/2012 |
$64,656,000 |
$636,000 |
$65,292,000 |
|
950061 |
12/31/2015 |
12/31/2015 |
$134,686,000 |
$0 |
$134,686,000 |
|
800672 |
12/31/2013 |
12/31/2013 |
$72,350,000 |
$0 |
$72,350,000 |
Other Associated Projects
Project PIN |
Project Description |
Status |
800673 |
In Development |
|
800696 |
In Development |
|
800684 |
In Development |
|
906687 |
Under Construction |
|
906725 |
RTE 17/I86 Interchange - Prospect High Mast Lighting, Phase 0 |
Project Complete |
906674 |
Under Construction |
|
906695 |
Project Complete |
|
906742 |
RTE 17/I86 Interchange - Phase 0A |
Project Complete |
906735 |
In Development |
|
950061 |
Under Construction |
|
950106 |
Under Construction |
|
950080 |
In Development |
|
980441 |
In Development |
|
906691 |
In Development |
|
906729 |
RTE 17/I86 Conversion Tioga County |
In Development |